The city says they’re about two thirds of the way done when it comes to finishing up the construction season. In some areas, the city says they’re ahead of schedule and starting today (mon) back lane reconstruction will begin. 95 per cent of back lane grading is already complete. The first coat of line painting is complete and now the city says a second coat of line painting is underway. For water and sewer replacement and work, approximately 70 per cent is complete across the city and of the city’s planned 206 kilometres of roadway improvements, 183 kilometres are complete.